Ardent DC-3 Campus

P—214

48 MW

IT load

Ardent DC-3 Campus

Ardent DC-3 Campus

Ardent DC-3 Campus

Client

Data-centre operator

Client

Data-centre operator

Location

Dallas, TX

Sector

Energy & Utilities

Delivery

MEP design-build

Value

$520M

Duration

27 months

Status

In progress

Year

2027

§ 01 — Overview

A 48 MW data hall energised in phases, with zero downtime

A 48 MW data hall energised in phases, with zero downtime

02

The challenge

The challenge

A 48 MW data hall that had to be energised in phases while earlier halls on the campus were already live.

A 48 MW data hall that had to be energised in phases while earlier halls on the campus were already live.

03

Engineering approach

Engineering approach

MEP systems were prefabricated as skid-mounted modules and every tie-in to live infrastructure was rehearsed in a digital model first.

MEP systems were prefabricated as skid-mounted modules and every tie-in to live infrastructure was rehearsed in a digital model first.

04

Execution

Execution

Each 12 MW phase passed integrated systems testing at the first attempt, with no impact on live customers.

Each 12 MW phase passed integrated systems testing at the first attempt, with no impact on live customers.

§ 05

Key metrics

48 MW

IT load

310

Prefab modules

0

Live-campus incidents

4 × 12 MW

Phases

Request for proposal

Planning somethingsimilar?

Tell us about scope, location, budget and timeline. A project director replies within two working days (sample commitment).

Start a proposal

Create a free website with Framer, the website builder loved by startups, designers and agencies.